| (cont from 809)
The Licensee stated that the permit for the converted garage was previously pulled and approved. The Licensee further reported that permit applications for the interior conversion of the home have been submitted and that he is currently working with the Los Angeles Department of Building and Safety to complete required corrections in order to finalize the permits.
LPM Margaryan informed the Licensee that although the facility currently has no residents, the facility license remains active. Therefore, pursuant to Title 22, California Code of Regulations prior to beginning any construction and/or renovation to a licensed facility the licensee must contact the Licensing Office for approval.
LPM Margaryan also advised the Licensee that follow-up actions will be required once the construction project is finalized.
1. Once DSS receives the final permit(s), DSS will verify the information with LADBS.
2. The Licensee must request a new fire clearance by submitting LIC 200 along with a new facility sketch. The sketch must clearly show how the licensed facility will be separated from the ADUs located at the rear of the property and identify all exits for both the facility and the ADUs.
3. A fire inspector will conduct an on-site inspection to review and approve the request.
4. Upon approval, the Licensing Office will update the facility records.
5. A new license will be issued reflecting the approved changes. The Licensing Department may conduct additional visits to verify that the physical plant mates the final approved sketch.
Licensee also was notified that a copy of this report will be e-mailed to him for manual signature.
|